








 |
    
Log Book for February 16, 2008
Summary Report
Crew 66 Reporting
Expedition Delta (MDRS Crew 66) Final Report
February 2 - 17, 2008
John Thaler - Commander
Anna Grinberg - Executive Officer
Perry Edmundson - Chief Engineer
Michele Faragalli - Surface Exploration Systems Engineer
Nasim Kaveh - Field Exploration Systems Engineer
Cheryl Wartman - Biologist
Kerry Cupit - Geologist
Arthur Guest - Open-ended Researcher
Introduction
Anna Grinberg & John Thaler
Expedition Delta (MDRS Crew 66) was Mars Society Canada's fourth
mission in their Expedition Mars Analogue Research Training Series
(ExMATS). During this mission three engineers and three scientists were
introduced to the systems at the Mars Desert Research Station (MDRS)
and all six also gained experience in conducting research in planetary
analogue environments. This was the first ExMATS mission to be
instructed by two graduates of previous ExMATS missions: John Thaler
(ExBeta) and Anna Grinberg (ExGamma). The ExMATS training program has a
hands-on curriculum that covers topics such as power generation, water
recycling systems, and extravehicular activities (EVAs). Another
important objective is the cross-training which occurs as each
crewmember teaches the crew about their area of expertise during an
informal evening lecture series as well as impromtu lessons in the
field. The training segments of the mission were a great success and
the ExDelta scientists were able to complete four science projects
which fulfilled the primary science objectives of the mission. The
engineers were also kept busy with numerous maintenance and engineering
projects. The details of these science and engineering projects are
summarized below.
Science Projects Summary
Soil Gas Analysis at MDRS as a Rapid Resource and Geologic
Assessment Tool
Kerry Cupit
The geology project aimed to locate in-situ resources of water and
methane close to the surface around the MDRS area with the idea that
future astronauts could use these techniques for locating drinking
water and fuel soon after landing on Mars. Getting equipment from Earth
to Mars is considerably expensive, so using resources found on Mars
would greatly benefit a surface mission. The concentrations of gases
such as methane and carbon dioxide in the soil provide clues to where
such resources might be located. If geologic faults are in the area,
then they are ideal places for gases to flow up from, and therefore
part of the project aimed to locate faults that could be sampled.
Eighteen holes were dug around a possible fault zone and the soil gases
measured from each hole. While there didn't appear to be measurable
resources of methane or water in the study area, a lot was learned
about working with equipment in the field and what may need to be
improved in order for astronauts to successfully find these resources.
In particular, the arid desert environment of the area around MDRS, and
ideally on Mars, means that scientists may have to dig deeper holes and
over a larger area in order to get accurate results. Advancements in
equipment will no doubt be made as well, reducing the sampling time
required for each hole from 15 minutes down to 5. It would be
worthwhile to perform a follow-up study at MDRS with improved equipment
and over multiple study sites.
Smart Small Logistics Container Research Project
Arthur Guest
The MDRS Smart Small Logistics Container Research Project is a joint
effort between Expeditions Delta and Epsilon (Crews 66 & 67). The
overall goal of the research is to field-test using RFID technology to
track supplies for future space missions and to examine operational
issues involved with using Small Logistics Containers. The goal of the
work done during Expedition Delta was to troubleshoot the system and
ensure that it is fully operational for testing during Expedition
Epsilon. This goal was completed successfully including the
reprogramming of 150+ RFID tags, finding a location that enables a
constant Bluetooth connection, overcoming Internet limitations and
developing operational plans for Expedition Epsilon. One of the
unexpected benefits of this work was the input from other crewmembers
on the possible uses of RFID-enabled containers to perform actions such
as tracking which EVA field samples were taken on. From data collected
during Expedition Delta, it appears that while the usage of
RFID-enabled containers may not be necessary for MDRS missions due to
the relatively small amount of supplies involved in a two-week mission,
these containers will provide time-savings and ease of operations for
long duration lunar or Martian campaigns.
Water Quality Analysis in a Martian Environment: LC50
Daphnia magna exposed to Green Hab Effluent
Cheryl Wartman
In this study effluent collected from the GreenHab of the Mars Desert
Research Station (MDRS) was used to expose Daphnia magna a serial
dilution of the water so that the lethal concentration could be
determined in a short term acute toxicity test. Due to the late arrival
of the Daphnia only a fraction of the planned experiments were
possible, however preliminary experiments used the grey water from the
cascade tank after the trickle tank, as it should be the most toxic, as
well as water from the tank after the UV filter. Grey water contains
Oasis soap, food leavings, and shower waste (sweat solids & hair)
and is the primary effluent from the MDRS Hab. Based on grey water
measurements from the outlet of the 110 gallon tank, the combination of
these wastes and the local water normally produces a pH between 7.8 and
8.2. Mortality counts were taken at 1, 12, 24, and 48-hrs for dilutions
of grey water and UV treated grey water. From these results it appears
that the water after the trickle tanks is more toxic than that taken
after the UV filter. It has been noted that ability extract and use
water sources available on Mars would be a key asset in a proposed
mission. This study contributes to the methodology development for
determination of water toxicity available in a martian
environment.
Extremophile Sample Collection Project
John Thaler
In cooperation with Shannon Rupert and her collaborators, ExDelta and
ExEpsilon are collecting rock and soil samples from the MDRS area for a
project that aims to identify extremophiles. These extremophiles
include halophiles, endoliths, and desert varnishes. During ExDelta 20
samples were collected from evaporite deposits which form as surface
water evaporates and leave behind the dissolved salts such as gypsum or
calcite. The areas sampled included Lith Canyon, Candor Chasma and
Factory Bench. These evaporite deposits are prime locations to look for
halophiles or salt-loving bacteria. The samples will be shipped back to
Earth and analyzed for the presence of halophilic organisms.
Engineering Summary
Perry Edmundson
The Expedition Delta crew faced many engineering challenges during our
two-week mission. Initially, even the basic necessities of power and
water proved hard to come by. Upon our arrival, the Hab was being
powered by a portable gasoline generator connected to two battery
chargers that were in turn connected directly to the Hab's main battery
bank. All of this was situated beside the Hab rather than in its proper
location in the Engineering area. The main diesel generator, Wendy, was
out of service while it waited for a new fuel pump. The water supply
was also being provided by a temporary setup that included having the
portable water tank on the trailer parked right beside the Hab and a
hose and portable pump running from the tank into the Hab through the
front airlock and up the stairs to the water tank in the attic. In
addition, the hot water heater was not functioning.
Our crew arrived late in the evening on Saturday, February 2, 2008 and
simply unloaded our gear and settled in for the night. The previous
crew was in quite a hurry to leave the following morning, so we had
very little time (less than two hours) for debriefing and training on
the operation and maintenance of the Hab systems and equipment. After
their departure, we got to work cleaning up the Hab and trying to
digest everything we had been told during our abbreviated training. It
seemed quite overwhelming at first, but the Engineering team
systematically evaluated each problem and determined the best course of
action. By Day 3, our first day of Sim, we had relocated the portable
gasoline generator and battery chargers to the Engineering area and
connected the generator to the main Hab power cable using some
electrical parts that Don Foutz brought us. On the same day, we began
pumping water from the main water tank in the Engineering area into the
attic tank in the Hab, using the main water pump connected to the
generator. The team was working extremely well together and everything
seemed to be going very smoothly...perhaps a little too smoothly.
Day 4 brought a new challenge. The gasoline generator that was our only
source of power began to leak oil at an ever-increasing pace. By the
end of Day 4, the generator was going through oil faster than it was
going through gasoline. The situation was becoming desperate. The crew
wondered how much longer we would be able to continue under these dire
circumstances.
The morning of Day 5 brought renewed hope with a visit from Don Foutz.
Upon his arrival, we packed up the decrepit generator, which was now
not only leaking oil from every orifice but also spitting out bolts,
and sent Perry with Don to Price to return it and buy a new one. While
they were gone, the crew went into power conservation mode, shutting
off everything they possibly could to avoid draining the Hab's battery
bank to an unrecoverable charge level. Several hours later, Don and
Perry returned with a shiny new Briggs & Stratton gas generator.
The Engineering team set to work commissioning the new generator and
soon it was up and running, providing power to the Hab and charging the
battery banks. Things were looking up.
A couple of days later, Don brought the new fuel filter for Wendy and
got her up and running again. The engineers then changed the oil and
connected Wendy to the main power cable to the Hab and gave the gas
generator a well-deserved break. Wendy provided ample power to bring
the Hab's battery bank back to full charge over the next two
days.
With the critical resource problems under control, the engineers set
out to tackle a new challenge. One of the ATVs, an older Kawasaki
model, was not functional and neither Mission Support nor the previous
crew had been able to provide an explanation. After some disassembly
and troubleshooting, we discovered a loose electrical connection in the
ignition and a clogged fuel valve. Both problems were rectified and
"The Green Monster" was fired up. It was used on several EVAs during
the remainder of the mission and became the engineers' favorite ATV,
sort of like an old-school muscle car - raw power and a few quirks
(like a grinding gear box and not being able to shift into
reverse).
The GreenHab was also brought back from a crippled state to near-full
functionality. All that remains is the running of some new wires from
the Hab to the GreenHab, installation of a new macerator pump and
repair of the automatic level sensor in the settling tanks.
The engineers completed several other objectives, including scouting a
route and laying a measured line for a new internet power cable between
the Hab and the peak of Hab Ridge, as well as digging and leveling a
spot beside the Hab for a concrete pad for a new battery bank.
The engineers also participated heavily in science and exploration EVAs
on foot, on ATV and even longer-distance EVAs in the "pressurized
rover".
The final triumph for the Engineering team was the long-awaited and
much-anticipated return of the hot water heater into service, thanks to
a new mixer valve delivered by Don. The last two days of the mission
included hot showers for the first time.
All in all, Expedition Delta was a huge success from an Engineering
standpoint. Many problems were solved, objectives were met and new
practical skills were acquired by the team. The engineers worked
extremely well together and contributed greatly to the overall success
of the mission. We leave MDRS in a much better functional state than we
found it.
Surface Exploration Systems
Michele Faragalli
Several EVA and ATV issues were resolved during Crew 66's
rotation:
* EVA suit #3 was patched up for tears in the crotch and leg (some
other suits may need some additional repair)
* EVA helmet #3 radio-mic was replaced using spare parts and works well
now
* EVA pack #5 was rewired so the air flows properly now
* All helmets were polished using scratch repair solution
* ATV#2 (aka the Green Monster) is now operational, there was a loose
connection in the starter and the fuel filter was cleaned out; however
the belt seems to be slipping and it is nearly impossible to get it
into reverse
* The ATV refueling station was reassembled and is now operational
(Note: * If fuel is low in tank, the flow is very low)
* The emergency box was mounted on ATV#1 and replenished
* Oil was changed in all 3 ATVs (and a record of oil changes is now
posted in the EVA prep room near the newly labeled ATV keys) Dip sticks
are now available for measuring gas level in ATVs (they are in
emergency box)
* 2 radios were disassembled in attempt to fix their mic
unsuccessfully, however they are operational when connected to the
helmet mics
* A 7th EVA radio was found and is now in use
* A battery box was made to organize the recharged batteries vs. the
uncharged ones
In addition to the aforementioned troubleshooting, the crew performed
23 EVAs including two pressurized rover EVAs (using the commander's
vehicle) to Factory Bench. The EVAs achieved the scientific and
research goals of the mission, while the engineering EVAs successfully
completed the following tasks:
* A scouting mission to determine the length of cable required to set
up a new satellite internet outpost on radio ridge
* Digging of a rectangular area between the green hab and the habitat
for the new battery banks
* Removed and subsequently re-skirting the hab for PR purposes
* Displaced the battery charges and the now deceased backup generator
to the engineering area
Some issues were encountered during the science EVAs where the gloves
were found to be cumbersome in lighting the BBQ lighter for sterilizing
the scoopula. Also, for EVAs that required significant amount of
physical effort, some helmets seemed to fog more than others. Scratch
remover and polisher were applied to the helmets, however for the best
prevention, applying a thin layer of soap to the inside of the helmets
is effective. Lastly, in pack #2 there seems to be a loose connection
to the fans as changing the user's posture will stop the air flow. This
could be looked into by the following crew.
Green Hab Systems
Nasim Kaveh
Regarding the greenhouse project, I was responsible for the growth and
vitality of a set of plants growing in soil. These plants were
initially planted by previous crews (62, 64 and 65) and consisted of
the followings: sweet corn, coriander cilantro, fern leaf, basil,
cherry belle radishes, radishes, plumy tomatoes, lettuce and onions. Most of the plants were planted in commercial soil and a few sets were
planted in a mixture of Utah soil and commercial soil (50/50).
Greenhouse maintenance consisted of checking three times a day the
greenhouse inside and outside temperature and humidity as well as
watering the plants as needed (every other day). The inside temperature
of the greenhouse is controlled with two propane heaters and two fans
which automatically open/close in order to keep a constant inside
temperature. However, the inside temperature is not always the same and
it varies a lot with the outside temperature. This might be explained
by the fact that the greenhouse is inherently not very well insulated.
A small change has been made in the location of the plants during our
rotation. By measuring the amount of Photosynthetically Active
Radiation (PAR) in the Green Hab with a quantum meter, we could
determine the optimal position for the plants to capture light energy
for use in photosynthesis. Consequently we moved the plants to the
eastern side of the greenhouse where they could receive the maximum
amount of PAR.
A set of plants from crew 65 were transplanted to bigger pots in
commercial soil and this was marked and dated. An important note was to
consider the soil in which plants were grown. Those sets of plants
grown in half Utah soil were more vulnerable and needed to be watered
more often. Also, since the Utah soil is desert soil, it does not
contain the variety or levels of nutriments available in commercial
potting soil. Hence, a solution of "food for plants" was used for
fertilization and this was a great success in rescuing these plants
:-).
Conclusion
Anna Grinberg & John Thaler
This concludes our final report of ExDelta and the experiences we have
had as a crew will be with us forever. The entire crew is looking
forward to meeting up again at space conferences (COSPAR & IAC)
where we will be presenting some of the work that we've completed
during our mission. The six trainees have preformed spectacularly here
and are certainly ready to participate in future research focused and
long duration missions. For now though we're all saying "goodbye" to
Mars and are ready to head back to Earth where hot water flows in
abundance and low-sodium food is normal!
|
|
|