Log Book for February 9, 2008
Commander's Check-In
John Thaler Reporting
Commander's Check-In Report
February 9, 2008
John Thaler
Crew Physical Status:
We are all famous film stars. You may have seen us in such films as a
yet to be produced Japanese documentary.
Time Departed/Returned from EVA:
EVA 12:
Time Departed: 08:00
Time Returned: 11:25
EVA 13:
Time Departed: 08:00
Time Returned: 09:42
EVA 14:
Time Departed: 12:36
Time Returned: 13:30
EVA 15:
Time Departed: 13:53
Time Returned: 18:54
Brief Narrative of Field Mission Results:
EVA 12: Posed for Japanese film crew helicopter overflight. Conducted
exploratory EVA to UTM 12 S 4250000 0519500 to practise Field
Documentation Methodology. Also climbed to summit of Phobos Peak to
enjoy view and take panorama.
EVA 13: Posed for Japanese film crew helicopter overflight. Finished
laying and measuring marker rope for Hab Ridge internet project.
EVA 14: Posed for Japanese film crew on ATV.
EVA 15: Conducted geology data collection EVA drilling and measuring at
4 sites.
EVA Data/Interpretations:
EVA 12: Site exploration conducted with two areas of interest
identified.
EVA 13: Length of marker rope to Hab Ridge is 320 m (as reported in
Engineering Report).
EVA 14: Satisfied Japanese film crew's required shots.
EVA 15: Most productive geology EVA on mission to date since data
collection has begun in earnest
Hab Maintenance:
The early morning start for EVAs 12 & 13 meant that both EVAs finished
with time for an early lunch and left time for two EVAs in the
afternoon. The crew not on EVAs took the opportunity to rest and
finish up or assess some small projects. A large supply drop of
equipment arrived today with new toys for the science lab. Wendy
(generator) was fixed with a new fuel pump and the Hab's power issues
are (hopefully) a thing of the past.
Report Transmission Schedule:
Reports already submitted:
EVA 14 (Arthur)
EVA 12 (Kerry)
Special Science (Kerry)
Engineering (Perry)
Reports to be submitted by 20:30:
Commander Report (John)
Journalist Report (Perry)
EVA 13 Report (Anna)
EVA 14 Report (Cheryl)
Plans for Tomorrow:
Sunday we will sleep in an extra hour to mark the halfway point of the
mission and to make up for our early mornings with the Japanese film
crew. We will not be conducting any long-range EVAs in the morning but
in the afternoon we will have another geology data collection EVA. The
morning will be a time for organization of the new science equipment
and maintenance of EVA suits.
Inventory:
Running low on juice crystals. Food stocks sufficient. Gas & Diesel
supply sufficient. Water was refilled today.
Support Requested:
Instructions for how and where to set up science equipment we received
today. We will provide an inventory of this tonight to RST by 20:30.
A response is not needed before tomorrow.
|
|
|