Log Book for May 2, 2003
General Engineering Report
Joan Roch & Simone Kosol Reporting
Generator/Electricity: Main generator Checked at 08:30 and 20:20. Ran without problem today, but still suffers from an oil leak. Maintenance from the outside is expected in the next few days.
08:30 Check:
Run time: 3367.7 hrs
Oil added: 1.5 quarts (after 12 hours)
North tank: 36 (in use)
South tank: 85 (not in use)
20:20 Check:
Run time: 3379.6 hrs
Oil added: 1.5 quarts (after 12 hours)
North tank: 34 (in use)
South tank: 85 (not in use)
Computers / Networking: network is up, Internet is available, printer works.
Water: internal tank refilled at 20:00 from 24 to 55 Gal.
Grey water: at 20:20, refill of tank for toilet flush with grey water from
basin in shower room.
GreenHab:
08:30 Check: (by mutants)
min/max at north door: 83°F left, 70°F right
min/max temp./hygrometer at shelf: 55°F/86°F; 19%/26%
current temperature/humidity: 86°F/19%
mercury thermometer at south door: 76°F
14:06 Check: (EVA6)
min/max at north door: 114°F left, 82°F right
min/max temp./hygrometer at shelf: 86°F/117°F; 9%/90%
current temperature/humidity: 113°F/10%
mercury thermometer at south door: 93°F
20:20 Check: (by mutants)
min/max at north door: 72°F left, 66°F right
min/max temp./hygrometer at shelf: 75°F/113°F; 10%/15%
current temperature/humidity: 75°F/15%
mercury thermometer at south door: 70°F
Next Report: 05.03.2003, in the evening
|
|
|