Log Book for March 10, 2003
General Engineering Report
Matt Bamsey Reporting

Generator/Electricity: Generator continues to run well since tuning with regulator control board. At 1650 hrs the Hobbs meter read 2732.5 hrs and oil read at appropriate levels.

Propane: At 1655 hrs the tanks measured: South 46%, North 6%, Furnace 63%.

Water: Internal tank filled at 1715 hrs from 22-53 gallons.

GreenHab: No progress made.

Everest Rover: Had assistance from the University of Michigan team in troubleshooting problems encountered on an EVA.

ARES Rover: No progress made.

Datalogger: No progress made.

Additional Activities: Basic planning for an Engineering/Hab maintenance EVA scheduled for tomorrow.

Worked on new table showing hab circuit breaker layout.

Helped fix structural problem with one of the MDRS suits.