Log Book for March 1, 2003
General Engineering Report
Matt Bamsey Reporting

Generator/Electricity: Frequency still holding steady at approximately 60 Hz. Checked oil - ok.

Propane: At 2115 hrs the tanks measured: South 69%, North 52%, Furnace 74%.

Water: The water tank was refilled from 5 to 55 gallons at 1630 hrs.

GreenHab: Suggested changes were made to power diagrams of the greenhouse. New revision to be sent out tomorrow.

Everest Rover: Untrained crew members were given an overview and training session on the Everest's systems. Wireless network was setup for one of the two PCs. Other general work completed.

Ares Rover: No new developments.

Datalogger: Discovered cause of bug which caused system to hang after boot up. Determined Toshiba laptop cannot properly output to speaker when running on battery power.

Additional Activities: Installed Celestron decal on to the Observatory.