Log Book for March 6, 2005
Commander's Check-In
Mike Turner Reporting
We all got here sort of late, but luckily there was enough daylight left for Adam (from crew 35) to show the inner & outer hab systems.
For reference - He explained:
- The procedure for operation of the temporary generator.
- How to run the greenhab system.
- The water systems.
- General In-hab procedure & systems.
We're now getting everybody settled & the basics for hab operation straightened out.
Over dinner we're going to try to forge out a schedule for for the next week, we're going to try and stay organized and stick to a schedule. If we can keep the hab systems running well we'll have plenty of time to take a serious look at our science goals & produce the desired results.
The reports we'll have in tonight: Engineering Report - We may or may not have a commanders report tonight, due to the lateness of all of our arrivals.
|
|
|